A 1.5 MW heat pump installation on an automotive paint shop pre-treatment line
Outcome
- Sector
- Automotive paint shop
- Load
- 1.5 MW installation, multiple units
An automotive paint shop in India replaced fuel-fired process heating on its pre-treatment line. It installed 1.5 MW of Tetra Heat Pump capacity, delivered as more than one unit, because a single machine tops out at 1,450 kW.
The heat pump took the loads inside its range. Alkaline degrease at 55 to 80°C, zinc phosphating at 50 to 60°C, the hot rinses between them, and paint shop AHU reheat. The ovens stayed on the existing plant. ED cure at 190°C, bake at 140 to 200°C and powder cure at 177 to 204°C are all beyond what an industrial heat pump delivers.
Energy cost for the duty fell by 65%, the installation avoids 400 tonnes of CO2 a year, and simple payback was 18 months.
What can a heat pump actually take in a paint shop?
It can take the pre-treatment line, and nothing downstream of it.
| Paint shop duty | Temperature | Heat pump |
|---|---|---|
| Alkaline degrease | 55 to 80°C | In range |
| Zinc phosphating | 50 to 60°C | In range |
| Hot rinses and component washing | 55 to 80°C | In range |
| Paint shop AHU reheat | Ambient dependent | In range |
| ED bath conditioning | 28 to 32°C | In range, as a cooling duty |
| ED cure oven | 190°C | Out of range |
| Bake oven | 140 to 200°C | Out of range |
| Powder cure oven | 177 to 204°C | Out of range |
That split is the engineering story of a paint shop retrofit. We build air source, water source and cascade units, delivering continuous output up to 120°C with ±0.5°C control. That covers every duty in the top half of the table. It covers none of the ovens below it.
Heating and cooling on the same line, at the same time
A paint shop repays a heat pump faster than its fuel bill alone would suggest. The reason is in the fifth row of that table.
The pre-treatment baths have to be held between 50 and 80°C. The electrodeposition bath, on the same line at the same time, has to be held at 28 to 32°C. That is a cooling duty. In most shops a chiller meets it by rejecting the heat to atmosphere. Nearby, fuel is burned to make heat of almost the same grade.
A heat pump reads those as one duty. It takes heat out of the loop that needs cooling and puts it into the baths that need heating. Both ends of the transfer are useful work. This installation was built around that recovery, not as a straight boiler swap.
What was installed
1.5 MW of capacity, and that is an installation, not a machine. A single Tetra Heat Pump unit reaches 1,450 kW, and total project capacity runs to 5 MW across multiple units. That changes what you allow for plant room space and for the incoming supply.
The units run refrigerants including R1234ze and R245fa. Control integrates with BMS, SCADA and PLC networks over Modbus and BACnet, so the bath setpoints stay in the system already holding them.
What changed
| Line | Value | What it covers |
|---|---|---|
| Installed capacity | 1.5 MW | More than one unit. Single-unit capacity is 1,450 kW |
| Energy cost for the duty | 65% lower | The pre-treatment heating load, not the whole paint shop |
| CO2 avoided | 400 tonnes a year | Fuel no longer burned for that duty |
| Simple payback | 18 months | On the energy cost saving |
Read the second row precisely. The 65% is the cost of heating that duty, not the shop’s total energy bill. It says nothing about the ovens, which burn what they always burned.
Why the saving is that size, and where it would not be
Two things put it there. The first is the lift. A pre-treatment duty between 50 and 80°C sits at the favourable end of a heat pump’s curve. Our water source units are rated at COP 4.5 to 5.2 at 60°C output. Performance falls as output rises toward the 120°C ceiling, so a plant asking for 110 or 120°C would not see this shop’s number.
The second is the fuel displaced. Against piped gas and furnace oil the breakeven COP is 1.0 to 1.2, and against LDO it is 0.56 to 0.67. To match the incumbent on running cost, a heat pump needs to return a little over one unit of heat per unit of electricity. Everything above that is margin, and at a pre-treatment lift there is plenty. The same arithmetic against a boiler is worked through on the blog.
It does not carry across to coal or biomass. Breakeven against solid fuel runs 3.3 to 6.5. Against those fuels the case for a heat pump is stack emissions, air quality, labour and customer audit, not running cost. A 65% cost saving against coal is not a figure to put in front of an energy manager.
What to check before you assume the same result
Your own breakeven COP sets the ceiling. It is your electricity price per kWh divided by the delivered cost of a useful kWh of heat from the fuel you burn now.
Your ovens stay. A pre-treatment retrofit shrinks a fuel bill. It does not close a fuel account.
Your sanctioned load goes up, and this catches plants out. Moving a 1.5 MW thermal duty onto electricity raises connected load. In Maharashtra the security deposit is twice the average billing cycle, recalculated annually, so a larger monthly bill pulls a larger deposit through. Gujarat computes it as though the whole load were a new service, not the increment. Budget for both.
Working the same sum on your plant
Put your tariff, your fuel price and your bath temperature into the calculator and see where the breakeven lands. The automotive page has the full load list, paint manufacturing the resin and let-down side, and the high temperature heat pump page the equipment detail. Other projects sit under case studies; a look at your load profile starts here.
Frequently asked questions
- Which paint shop loads can an industrial heat pump serve?
- It took the pre-treatment line. Alkaline degrease runs 55 to 80°C, zinc phosphating 50 to 60°C, and the hot rinses and component washing between them sit in the same band. Paint shop AHU reheat is also in range. These are the duties an industrial heat pump can take over in an automotive paint shop.
- Can a heat pump run a paint shop curing oven?
- No. ED cure runs at 190°C, bake ovens at 140 to 200°C and powder cure at 177 to 204°C. Our units deliver continuous output up to 120°C. Every oven in a paint shop therefore stays on the plant that was already firing it. A retrofit reduces the fuel bill. It does not end it.
- Was the 1.5 MW a single machine?
- No. A single Tetra Heat Pump unit reaches 1,450 kW, so 1.5 MW of installed capacity is more than one unit. Total project capacity runs to 5 MW across multiple units. The distinction matters for plant room space and for the electrical connection.
- What was the payback on the paint shop installation?
- Simple payback was 18 months, calculated on the energy cost saving alone. Energy cost for the pre-treatment heating duty fell by 65% and the installation avoids 400 tonnes of CO2 a year.
- Does a heat pump help with the electrodeposition bath?
- Yes, and it is the part of a paint shop most often missed. The ED bath is held at 28 to 32°C, which is a cooling duty. The pre-treatment baths a few metres away need 50 to 80°C of heat. A heat pump can move heat from one to the other, instead of running a chiller and a burner against each other.
Can a heat pump carry this duty in your plant?
Send us the output temperature, the flow or heat demand, the hours it runs and the fuel it burns today. Our engineers will size a unit against those figures and tell you which part of the load it can take and which part stays on the heating you run today.